An equipment maintenance scheduler on AWS for a few dollars a month
The service was due in March. March was the busiest month of the year, so it slipped to April, and April slipped to May because the part was on back order, and in June the bearing failed during a production run. Nobody made a bad decision at any point; there was simply no place where the accumulated slippage was visible. This post walks through a small system built around that.

Key takeaways
- Schedule on running hours where they exist, on calendar where they do not.
- Deferral is normal and must be recorded with a reason and a name.
- Statutory inspections are a separate track and cannot be deferred at all.
- Over-maintenance is a real cost, and intervention itself causes failures.
- Designed on AWS for about $2 a month.
The whole system on one page
Before any code, here is the shape of what we are designing.
- Compute
- Database
- Management
- Analytics
- People
Deferral is the design problem
Every maintenance system schedules jobs. The ones that fail in practice fail because reality intervenes: the machine is needed, the engineer is ill, the part has not arrived, the job is genuinely less urgent than the thing it would displace.
When there is no way to record that, the job simply stays overdue, the overdue list grows until it is meaningless, and everybody starts ignoring it. Making deferral a real action with a reason and a new date keeps the list short enough to be believed, and turns the accumulated slippage into something visible.
What runs (the inside)
- The usage tracker. Records running hours or cycles and works out how much each machine has done since it was last serviced. Part 2.
- The due list. A short, ordered list of what needs doing, with its urgency and its consequence. Part 2.
- The deferral record. Who moved a job, why, until when, and what the cumulative picture looks like. Parts 3, 4 and 5.
One machine, end to end
- Compute
- Management
- Analytics
In plain words
A machine was last serviced at four thousand two hundred running hours and the interval is five hundred hours. It has now done four hundred and forty since, which is eighty-eight per cent of the way. At ninety per cent it appears on the due list, which is early enough to arrange and late enough not to clutter.
The part needed is on back order, so the job is deferred by two weeks with that reason and the name of whoever decided. It stays on the list, marked deferred rather than overdue, and the reason is visible next to it.
If it is deferred again the system says so explicitly: second deferral, now at a hundred and twelve per cent of interval. A third deferral triggers a different conversation. Nothing is blocked, nothing is automated, and the accumulated position is impossible to lose track of.
Design rules that shaped every decision
- Usage where it exists, calendar where it does not, and say which is being used.
- Deferral is a recorded action with a reason, a name and a new date.
- Statutory inspections are a separate track with no deferral action at all.
- The due list is short. Anything longer than a day’s work is not a list, it is a backlog.
- Never auto-close a job. A completed job is somebody saying they did it.
- Record the parts needed with the job, because parts are why most deferrals happen.
Why this shape
Maintenance software is usually built around the work order and treats scheduling as arithmetic. That is the wrong emphasis for a small operation, where the arithmetic is trivial and the actual difficulty is that there are more jobs than hours and somebody has to choose.
So this design puts its weight on making that choice visible: what is due, what has been put off, how far past due things are, and which machine keeps appearing. The scheduling is the easy half and it is not where the failures come from.
The next four posts walk through each piece: how the interval gets decided, how a deferral gets recorded, which jobs cannot be deferred, and what the history tells you. One diagram per post, a cost breakdown, and an engineering reference at the end.